1. Annual production of 200,000 tons biomass pellets manufacturing project (Phase 1)
(1) Total budget investment: 95 million yuan
(2) Project status: construction preparation
(3) Project location: Siping City, Jilin Province
(4) Project construction details: The project covers an area of 6,650 square meters, with a total construction area of 4,000 square meters, an annual output of 100,000 tons of biomass pellets, and a treatment of 100,000 tons of straw per year.
(5) Specific progress:
①Procedures of procedures: The project is still undergoing environmental assessment procedures.
②Design completion status: The design has not yet started, and RICHI is responsible for the design.
③Civil construction: the main body has not yet started, and the specific time has not been determined.
④Equipment situation: The equipment will start production in April.
⑤Estimated project commissioning time: the end of 2021
2. Biomass straw pellet fuel production plant project
(1) Total budget investment: 1 billion yuan
(2) Project status: project approval application
(3) Project location: Chifeng City, Inner Mongolia
(4) Project construction details: The total area of the project is 133,017 square meters, which is divided into two phases of construction.
(5) Specific progress:
①Procedures of procedures: Procedures of procedures: The project is undergoing preliminary procedures.
②The completion of the design: the design has not yet started, and the specific start-up time has not yet been determined.
③Civil construction: the main project has not been constructed yet, and the construction unit has not yet been determined.
④Equipment situation: The equipment will start production in June.
⑤Estimated project commissioning time: April 2022
3.Complete annual output of 50,000 tons straw biomass pellet comprehensive recycling project
(1) Total budget investment: 397,836,900 yuan
(2) Project status: engineering design
(3) Project location: Tonghua City, Jilin Province
(4) Details of project construction: The total area of the project is 3900 square meters, which is divided into two phases of construction.
(5) Specific progress:
①Procedures of procedures: Procedures of procedures: The project is undergoing environmental assessment procedures.
②Design completion status: Preliminary design will be carried out simultaneously, and RICHI will be responsible.
③Civil construction status: The main project has not yet been constructed, and bidding will be invited later.
④Equipment situation: The equipment will start production in May.
⑤Estimated project commissioning time: the end of 2021